Project progress

Confirmed milestones and updates.

Key information on the delivery of the Rietavas battery energy storage facility.

17 APR 2025Capacity reservation
01

Letter of intent signed with Litgrid

The letter of intent reserved the grid capacity required for the project.

29 MAY 2025Development permit
02

VERT issued the energy storage development permit

The National Energy Regulatory Council issued the permit required to develop the project.

15 OCT 2025Building permit
03

Building permit obtained

The construction permit required to deliver the project was issued.

06 NOV 2025EPC contract
04

€27.8 million EPC contract signed

MT Group will engineer, construct and commission the Rietavas battery energy storage system.

09 DEC 2025Financing
05

Artea Bank finances the project

The financing partnership provides a strong foundation for the delivery of strategically important energy infrastructure.

01 MAR 2026Earthworks
06

TETAS commenced active earthworks on site

Site preparation and the principal earthworks commenced.

07 JUL 2026Equipment delivery
07

All critical equipment delivered to site

Power conversion systems (PCS), batteries and other essential BESS equipment arrived on site.

07 SEP 2026Cold commissioning
08

Cold commissioning begins

System checks and cold commissioning are scheduled to begin before power is supplied to the grid.